Sl.No | Informal Review | Formal Review |
1 | Conducted on an as-needed I.e. Informal agenda | Conducted at the end of each life cycle phase I.e. Formal Agenda |
2 | The date and the time of the agenda for the Informal Review will not be addressed in the Project Plan | The agenda for the formal review must be addressed in the Project Plan |
3 | The developer chooses a review panel and provides and/or presents the material to be reviewed | The acquirer of the software appoints the formal review panel or board, who may make or affect a go/no-go decision to proceed to the next step of the life cycle. |
4 | The material may be as informal as a computer listing or hand-written documentation. | The material must be well prepared. Ex Formal reviews include the Software Requirements Review, the Software Preliminary Design Review, the Software Critical Design Review, and the Software Test Readiness Review. |